A can do a piece of work in 10 days , B can do the same in 30 days and c in 60 days . If A is assisted on alternate days by B and C, in how many days would the work get completed?
বিকল্পসমূহ (নিজের উত্তর যাচাই করতে ক্লিক করুন):
সঠিক উত্তর
3 (8)