A and B together can complete a piece of work in 12 days, B and C can do it in 20 days and C and A can do it in 15 days. A , B and C together can complete it in.
বিকল্পসমূহ (নিজের উত্তর যাচাই করতে ক্লিক করুন):
সঠিক উত্তর
3 (10 days)