A can complete a piece of work in 12 days, A, B and C can complete the work in 6 days, Efficiency of B is 0.5 times the efficiency of In how many days C can complete the works= alone?
বিকল্পসমূহ (নিজের উত্তর যাচাই করতে ক্লিক করুন):
সঠিক উত্তর
ক (24 days)